Events
Events
220kV TMSC Line from 400kV SS Hindupur to 220kV SS Hindupur test charged on 24-02-2022 at 16:14 Hrs
- Presently the 220/132/33 kV SS Hindupur is fed from 220kV Gooty Shyapuram - Hindupur at a length of 159.1km and the second source from 220kV Pulivendula - Gollapuram - Hindupur line at a length of 143.88km
- After charging of above line which is having lesser length of 15.7km from 400kV SS Hindupur to 220kV SS Hindupur
Advantages
- Voltage profile is improved
- Line losses are reduced
- Reliability of power is maintained for 220kV substation Hindupur