| Anantapur |
ECV 4,33,45,63,050 Crs Budget Estimates FY-22 1,00,99,28,650 Crs Financial Progress(%) 23.2%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| BL-19-01-01 |
132 DC/SC LN-RAYADURG SS-RTSS RAYADURG |
PRIMUL INFRA |
21-08-2020 |
20-02-2021 |
6,09,37,977.32 |
0.00 |
0 |
| BL-19-01-02 |
132KV BAY EXTENSION AT 132KV RAYADURG SS |
PRIMUL INFRA |
21-08-2020 |
20-02-2021 |
1,26,00,337.75 |
0.00 |
0 |
| BL-19-01-03 |
METERING BAYS AT RTSS RAYADURG |
PRIMUL INFRA |
21-08-2020 |
20-02-2021 |
59,85,658.53 |
0.00 |
0 |
| PE-12-02-09 |
220KVDCLN400KVTALAMPATNAM-TADIPATRI |
MEGHA ENGINEERING & INFRASTRUCTURES |
05-01-2018 |
04-04-2019 |
21,64,11,631.92 |
0.00 |
0 |
| PE-12-02-27 |
220 KV BAYS AT 220KV SS TADIPATRI |
MEGHA ENGINEERING & INFRASTRUCTURES |
05-01-2018 |
|
2,89,24,423.51 |
0.00 |
55.34 |
| PE-12-02-27 |
220 KV BAYS AT 220KV SS TADIPATRI |
STERLITE POWER TRANSMISSION LIMITED |
05-01-2018 |
|
55,41,947.81 |
0.00 |
0 |
| PE-12-03-01 |
HINDUPUR-PAMPANURTANDA 220 KV TMDC LINE |
KMV PROJECTS LIMITED |
07-06-2018 |
30-04-2021 |
88,97,68,668.56 |
8,48,87,366.00 |
18.35 |
| PE-12-03-01 |
HINDUPUR-PAMPANURTANDA 220 KV TMDC LINE |
HYDERABAD POWER INSTALLATIONS PVT L |
15-03-2018 |
|
15,34,000.00 |
0.00 |
0 |
| PE-12-03-02 |
220/132KV SS AT PAMPANUR TANDA |
KMV PROJECTS LIMITED |
07-06-2018 |
30-04-2021 |
21,88,47,128.37 |
88,08,100.00 |
87.67 |
| PE-12-03-09 |
ESIA & ESMP OF ELECTRICAL PROJECTS-ATP |
CHOLAMANDALAM MS RISK SERVICES LTD |
09-02-2018 |
|
23,60,000.00 |
0.00 |
0 |
| PE-12-03-13 |
220KV DC LN 400KV HDPR TO 220KV HDPR |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
|
26,27,18,578.92 |
6,52,08,539.00 |
24.82 |
| PE-12-03-14 |
220KV DC LN 400KV HDPR TO GOLLAPURAM |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
28-10-2020 |
40,04,56,502.87 |
21,65,93,752.00 |
54.08 |
| PE-12-03-15 |
2 NOS 220KV BAY AT 400KV HINDUPUR(SCH-B3 |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
|
33,40,47,633.34 |
1,66,88,413.00 |
4.99 |
| PE-12-03-16 |
HDPR-PMPNRTANDA 220 KV SMDC LINE |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
|
58,60,30,770.41 |
78,68,508.00 |
1.34 |
| PE-12-03-17 |
2 NOS. 220KV BAY AT PAMPANURTANDA |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
|
3,03,07,295.20 |
69,38,222.00 |
22.89 |
| PE-12-03-19 |
220KV DC LN 400KV HDPR - 220KV PENUKONDA |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
|
33,86,18,727.10 |
39,97,058.00 |
1.18 |
| PE-12-03-22 |
1 NO 220KV BAY AT 400KV HINDUPUR(SCH-C2) |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
|
3,69,66,269.38 |
55,39,241.00 |
14.98 |
| PE-12-03-23 |
1 NO 220KV BAY AT 220KV HINDUPUR(SCH-C3 |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
|
1,88,17,619.01 |
68,50,874.00 |
36.40 |
| PE-12-03-24 |
2 NOS 220KV BAY AT 220KV GOLLAPURAM |
AMARA RAJA POWER SYSTEMS LIMITED |
29-03-2019 |
28-10-2020 |
3,36,05,252.32 |
81,38,764.00 |
24.21 |
| SI-12-17-01 |
220KV DC LN-LILO OF GOOTY-SHAPURAM SC LN |
PMR CONSTRUCTIONS INDIA PVT.LTD. |
11-03-2020 |
|
9,61,83,883.69 |
4,19,20,963.00 |
43.58 |
| SI-12-17-02 |
132KV DC LINE-132KV DHARMVRM-220DHARMVRM |
PMR CONSTRUCTIONS INDIA PVT.LTD. |
11-03-2020 |
|
5,27,65,802.55 |
7,43,040.00 |
1.40 |
| SI-12-17-04 |
220/132KV SS DHARMAVARAM,ATP DIST. |
PMR CONSTRUCTIONS INDIA PVT.LTD. |
11-03-2020 |
|
18,62,76,802.97 |
6,24,76,005.00 |
33.53 |
| SI-12-17-05 |
132KV BAY EXTENSION AT 132KV DHARMAVARAM |
PMR CONSTRUCTIONS INDIA PVT.LTD. |
11-03-2020 |
|
1,43,58,570.68 |
12,91,519.00 |
8.99 |
| SI-12-18-01 |
132KV DC/SC LINE KADIRI-MUDIGUBBA |
BASIL PROJECTS (JV WITH SRI HARI CO |
09-07-2020 |
|
5,37,65,913.90 |
7,40,362.00 |
1.37 |
| SI-12-18-02 |
132/33 KV SS MUDIGUBBA |
BASIL PROJECTS (JV WITH SRI HARI CO |
09-07-2020 |
|
6,20,07,378.24 |
19,71,758.00 |
3.17 |
| SI-12-18-03 |
CKT-2 STRING-KADIRI-PULIVENDULA-ATP RGN |
RR DURAFABS PRIVATE LIMITED |
25-02-2020 |
|
1,24,20,479.07 |
0.00 |
0 |
| SI-12-18-04 |
BAY EXTEN. AT PULIVENDUAL(1NO BAY) |
RR DURAFABS PRIVATE LIMITED |
25-02-2020 |
|
1,24,30,493.06 |
0.00 |
0 |
| SI-12-18-05 |
BAY EXTEN. AT KADIRI (2 NO BAYS) |
RR DURAFABS PRIVATE LIMITED |
25-02-2020 |
|
1,60,82,234.04 |
0.00 |
0 |
| SI-12-18-06 |
CKT-2 STRING-KADIRI-PULIVENDULA-KDP RGN |
RR DURAFABS PRIVATE LIMITED |
25-02-2020 |
|
85,44,762.85 |
0.00 |
0 |
| SI-16-02-02 |
ERECTION OF220 KV DC LINE PVL-HDP R-II |
KOTAGI STRUCTURALS |
06-11-2018 |
|
43,64,334.00 |
0.00 |
145.98 |
| SI-16-02-03 |
ERECTION OF220 KV DC LINE PVL-HDP R-I |
KOTAGI STRUCTURALS |
04-10-2018 |
|
48,10,150.08 |
0.00 |
129.97 |
| SI-16-02-03 |
ERECTION OF220 KV DC LINE PVL-HDP R-I |
PVR CONSTRUCTIONS |
24-10-2018 |
|
2,61,301.31 |
0.00 |
0 |
| SI-16-27-01 |
132/33KV SUB-STATION AT PALASAMUDRAM |
MYTRAH ENGINEERING & INFRASTRUCTURE |
23-11-2018 |
22-05-2019 |
10,02,20,306.33 |
29,73,495.00 |
66.08 |
| SI-16-27-02 |
2ND CKT FROM 220KV SS GOLLAPURAM-LEPAKSH |
MYTRAH ENGINEERING & INFRASTRUCTURE |
23-11-2018 |
22-05-2019 |
2,30,60,948.60 |
0.00 |
164.56 |
| SI-16-27-03 |
132KV DC LINE FROM LEPAKSHI-PALASAMUDRAM |
MYTRAH ENGINEERING & INFRASTRUCTURE |
23-11-2018 |
22-05-2019 |
11,31,28,217.82 |
23,39,942.00 |
21.27 |
| SI-16-27-04 |
1NO 132KV BAY EXT. AT 220KV GOLLAPURAM |
MYTRAH ENGINEERING & INFRASTRUCTURE |
23-11-2018 |
22-05-2019 |
81,49,172.95 |
4,70,213.00 |
59.37 |
| SI-16-27-05 |
3NO BAY EXTNS. AT 132KV LEPAKSHI SS |
MYTRAH ENGINEERING & INFRASTRUCTURE |
23-11-2018 |
22-05-2019 |
1,94,87,485.75 |
9,33,486.00 |
50.43 |
| SI-16-28-01 |
33KV FEATURES AT 132/33KV MADAKASIRA SS |
BASIL PROJECTS (JV WITH SRI HARI CO |
09-07-2020 |
08-04-2021 |
2,75,98,861.97 |
26,92,981.00 |
9.75 |
| SI-18-13-03 |
2ND CKT SUBBARAYUNIPALLI-ERRAMANCH-AP14 |
P.CHANDRA REDDY & Co. |
28-03-2019 |
31-03-2019 |
83,06,437.39 |
1,69,230.00 |
270.17 |
| SI-18-13-04 |
220KV BAY EXTEN. AT 220/11 BOKSAMPALLI |
P.CHANDRA REDDY & Co. |
28-03-2019 |
31-03-2019 |
1,71,08,104.62 |
2,40,488.00 |
30.73 |
| SI-18-13-05 |
BAY EXTEN. AT 220/11KV SUBBARAYUNIPALLI |
P.CHANDRA REDDY & Co. |
28-03-2019 |
31-03-2019 |
87,50,985.56 |
74,337.00 |
66.63 |
| Chittoor |
ECV 1,06,37,68,387 Crs Budget Estimates FY-22 31,27,65,471 Crs Financial Progress(%) 29.4%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| SI-10-16-02 |
132KV BAY AT SRIKALAHASTI 132KV SS |
P.CHANDRA REDDY & Co. |
19-11-2013 |
|
3,07,288.43 |
2,62,606.00 |
85.45 |
| SI-10-16-03 |
2ND CKT SRIKALAHASTI-VENKATAGIRI |
P.CHANDRA REDDY & Co. |
19-11-2013 |
|
49,80,003.76 |
66,80,241.00 |
134.14 |
| SI-15-28-02 |
132KV 2ND CKT STRG NAGARI-PACHKPLM |
P.CHANDRA REDDY & Co. |
03-12-2018 |
|
4,36,66,491.27 |
21,16,400.00 |
55.71 |
| SI-16-26-01 |
132/33 KV SS, Mangalam |
STERLING AND WILSON PRIVATE LTD |
17-12-2018 |
|
8,98,22,227.16 |
29,27,843.00 |
6.44 |
| SI-16-26-02 |
132KV DC lne Rachaganneri SS-Mangalam SS |
STERLING AND WILSON PRIVATE LTD |
17-12-2018 |
02-04-2020 |
16,40,96,951.19 |
97,72,056.00 |
27.18 |
| SI-16-26-03 |
132KV BAY AT 220KV Rachagunneri SS |
STERLING AND WILSON PRIVATE LTD |
17-12-2018 |
|
2,04,76,311.34 |
15,87,553.00 |
16.07 |
| SI-19-10-02 |
220/132 KV SS CHERVI (RACHERLA) |
LAXMI TRANSMISSIONS |
13-03-2020 |
12-03-2021 |
17,65,38,546.97 |
2,91,44,151.00 |
16.50 |
| SI-19-10-03 |
220KV DC LINE RACHAGUNNERI- CHERVI (RACH) |
LAXMI TRANSMISSIONS |
13-03-2020 |
12-03-2021 |
40,99,21,368.44 |
16,03,09,446.00 |
39.10 |
| SI-19-10-04 |
220KV DC LN SULLURPETA- CHERVI (RACHERLA |
LAXMI TRANSMISSIONS |
13-03-2020 |
12-03-2021 |
13,09,50,934.00 |
3,57,83,459.00 |
27.32 |
| SI-19-10-05 |
2NO 220KV BAY EXTENSION AT SULLURUPET SS |
LAXMI TRANSMISSIONS |
13-03-2020 |
12-03-2021 |
2,30,08,264.15 |
25,66,913.00 |
11.15 |
| East Godavari |
ECV 58,31,76,755 Crs Budget Estimates FY-22 8,08,19,212 Crs Financial Progress(%) 13.8%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| PE-18-01-05 |
220KV DCLN PURUSHOTHAPATNAM-GDGUDEM-5109 |
MEGHA ENGINEERING & INFRASTRUCTURES |
21-01-2020 |
|
3,33,25,567.21 |
0.00 |
0 |
| PE-18-01-07 |
2NO 220KV BAY EXTN.AT PURUSHOTHAPATNAM |
MEGHA ENGINEERING & INFRASTRUCTURES |
21-01-2020 |
|
2,63,60,296.28 |
12,63,016.00 |
4.79 |
| SI-10-11-01 |
2ND CKT STRINGING ON NARASAPUR-RAZOLE |
K.RAMACHANDRA RAO TRANSMISSION & |
16-07-2011 |
|
10,85,299.64 |
0.00 |
0 |
| SI-18-02-01 |
220/33KV SS CHINTURU,RJY |
VERTEX ENGINEERS |
03-12-2018 |
25-10-2021 |
11,79,00,907.62 |
0.00 |
0 |
| SI-18-02-02 |
LILO OF 220KV LOWER SILERU-KTS-II |
VERTEX ENGINEERS |
03-12-2018 |
|
5,65,96,892.28 |
0.00 |
0 |
| SI-18-03-01 |
132KV&33KV FEATURE AT 220/11KV RAMAVARAM |
SREE LAKSHMI ELECTRICAL SERVICES |
12-03-2019 |
17-02-2020 |
9,70,03,119.71 |
0.00 |
0 |
| SI-18-03-02 |
LILO OF 132KV PEDDAPURAM-PRATHIPADU LINE |
SREE LAKSHMI ELECTRICAL SERVICES |
12-03-2019 |
19-03-2020 |
14,97,89,142.06 |
0.00 |
0 |
| SI-18-04-01 |
220/33KV SS bavojipeta(korukonda) |
P.CHANDRA REDDY & Co. |
31-10-2018 |
31-07-2020 |
10,11,15,530.57 |
1,40,55,384.00 |
78.67 |
| Guntur |
ECV 2,90,87,24,578 Crs Budget Estimates FY-22 46,32,65,240 Crs Financial Progress(%) 15.9%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| BL-17-01-01 |
132KV METERINGBAY AT RTSS GURAZALA |
R.K.ELECTRIC AUTOMATION LIMITED |
21-05-2018 |
02-02-2019 |
46,24,857.35 |
7,06,015.00 |
375.81 |
| BL-17-01-02 |
BAY AT RENTACHINTALA FOR RTSS GURAZ |
R.K.ELECTRIC AUTOMATION LIMITED |
21-05-2018 |
02-02-2019 |
80,97,087.71 |
0.00 |
13.27 |
| BL-17-01-03 |
132KV 2PH DC/SC LN FOR RTSSGURAZALA |
R.K.ELECTRIC AUTOMATION LIMITED |
21-05-2018 |
02-02-2019 |
3,50,18,369.73 |
14,44,672.00 |
11.51 |
| SI-10-12-01 |
132KV BAY EXTENSION AT MACHERLA SS |
SRI BALAJI INFRA PROJECTS |
21-03-2018 |
01-02-2018 |
21,86,107.76 |
0.00 |
25.91 |
| SI-10-12-02 |
132 KV LINE FROM MACHERLA SS |
KMV PROJECTS LIMITED |
17-11-2016 |
05-10-2018 |
17,29,520.58 |
0.00 |
0 |
| SI-10-12-02 |
132 KV LINE FROM MACHERLA SS |
SRI BALAJI INFRA PROJECTS |
17-09-2016 |
01-02-2018 |
1,92,91,463.90 |
0.00 |
0 |
| SI-10-12-02 |
132 KV LINE FROM MACHERLA SS |
SRI BALAJI INFRA PROJECTS |
21-03-2018 |
01-02-2018 |
2,43,23,234.83 |
3,48,232.00 |
84.61 |
| SI-10-12-03 |
132/33 KV SS VELDURTHY (UPPALAPADU) |
SRI BALAJI INFRA PROJECTS |
21-03-2018 |
01-02-2018 |
2,24,59,942.61 |
61,378.00 |
67.43 |
| SI-13-04-02 |
220KV BAYS AT SATTENPALLI 400KV SS |
KMV PROJECTS LIMITED |
17-11-2016 |
31-08-2020 |
5,87,21,967.74 |
2,47,304.00 |
56.97 |
| SI-13-04-04 |
220/132KV SS GUNTUR |
KMV PROJECTS LIMITED |
17-11-2016 |
31-08-2020 |
21,46,67,665.22 |
35,63,445.00 |
63.47 |
| SI-16-24-01 |
220/132KV GIS SS AT LINGAYAPALEM |
MEGHA ENGINEERING & INFRASTRUCTURES |
29-10-2018 |
21-09-2020 |
63,82,91,712.77 |
0.00 |
29.40 |
| SI-16-24-02 |
LILO OF 220KV PODILI TO LINGAYAPALEM |
MEGHA ENGINEERING & INFRASTRUCTURES |
29-10-2018 |
|
49,91,74,958.20 |
0.00 |
0 |
| SI-17-06-01 |
132/33 KV SS AIIMS AT MANGALAGIRI |
ANNAPURNA CONSTRUCTIONS & TRANSMISS |
16-05-2018 |
27-02-2019 |
6,90,73,264.53 |
62,64,496.00 |
55.39 |
| SI-17-06-02 |
LILO OF 132KV TDPALLI-TATI AT AIIMS |
ANNAPURNA CONSTRUCTIONS & TRANSMISS |
16-05-2018 |
28-12-2020 |
1,57,88,979.48 |
87,85,747.00 |
55.64 |
| SI-17-25-01 |
TADIKONDA-MARRIPALEM LILO TO GUJJANAGUND |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
|
1,10,60,670.83 |
0.00 |
0 |
| SI-17-25-02 |
132KV BAY EXTENSION AT 132KV Gujjanagund |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
|
80,38,463.59 |
0.00 |
0 |
| SI-18-18-02 |
Nelapadu Line |
STERLING AND WILSON PRIVATE LTD - ( |
19-08-2019 |
20-09-2020 |
1,11,25,37,739.50 |
0.00 |
0 |
| SI-18-28-01 |
2ND CKT STRINGING-RAPALLE-CHAKRAYAPALEM |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
4,09,58,278.95 |
0.00 |
0 |
| SI-18-28-02 |
132KV BAY EXTENSION AT 132KV REPALLE SS |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
51,41,044.97 |
0.00 |
0 |
| SI-18-28-03 |
132KV BAY EXTN AT 132KV CHAKRAYAPALEM SS |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
50,42,089.60 |
0.00 |
0 |
| SI-18-29-01 |
2ND CKT STRINGING ON 132 RAPALLE-BAPATLA |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
3,13,85,101.54 |
0.00 |
0 |
| SI-18-29-02 |
132KV BAY EXTENSION AT 132KV REPALLE SS |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
49,25,397.56 |
0.00 |
0 |
| SI-18-29-03 |
132KV BAY EXTENSION AT 132KV BAPATLA SS |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
51,99,589.55 |
0.00 |
0 |
| SI-18-38-01 |
2NDCKT STRINGING-TADIKONDA-GUJJANAGUNDLA |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
70,62,372.51 |
0.00 |
0 |
| SI-18-38-02 |
132KV BAY EXTN AT 132KV TADIKONDA SS |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
47,33,947.45 |
0.00 |
0 |
| SI-18-38-03 |
132KV BAY EXTN AT 132KV GUJJANAGUNDLA SS |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
44,11,362.16 |
0.00 |
0 |
| SI-18-44-01 |
2ND CKT STRNG FROM 132KV MARTUR-YADAVALI |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
4,45,06,963.36 |
0.00 |
0 |
| SI-18-44-02 |
132KV BAYS AT 132KV MARTUR SS |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
52,34,202.98 |
0.00 |
0 |
| SI-18-44-03 |
132KV BAYS AT 132KV YADAVALI SS |
A.R. CONSTRUCTIONS PVT LTD |
22-09-2020 |
26-05-2021 |
50,38,221.13 |
0.00 |
0 |
| Kadapa |
ECV 6,17,95,00,843 Crs Budget Estimates FY-22 4,12,36,44,330 Crs Financial Progress(%) 66.7%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| PE-12-02-18 |
URAVAKONDA - JAMMALAMADUGU 400KV LI |
LARSEN & TOUBRO LIMITED |
28-07-2016 |
|
46,33,079.53 |
0.00 |
1999.09 |
| PE-12-02-19 |
URAVAKONDA - YEMMIGANOOR 400 KV QMD |
TATA PROJECTS LIMITED |
16-12-2013 |
|
1,87,06,284.07 |
0.00 |
262.07 |
| PE-12-02-21 |
TB RIVER TO YEMMIGANOOR 400 KV QMDC |
LARSEN & TOUBRO LIMITED |
11-06-2014 |
31-10-2015 |
4,49,62,146.17 |
0.00 |
46.83 |
| PE-12-02-23 |
ERECTION OF 400 KV SS AT JAMMALAMADUGU |
TECHNO ELECTRIC & ENGINEERING CO.LT |
21-05-2014 |
|
7,15,707.12 |
0.00 |
12.80 |
| PE-12-03-03 |
BAY FR 3RD 315 MVA & 80 MVA REACT AT JMD |
TATA PROJECTS LIMITED |
31-03-2016 |
|
7,61,49,362.28 |
3,66,819.00 |
28.05 |
| PE-12-03-04 |
400 KV BAY EXTENSIONS AT URAVAKONDA |
TATA PROJECTS LIMITED |
31-03-2016 |
|
10,91,19,792.68 |
3,32,778.00 |
77.16 |
| PE-12-03-05 |
400 KV BAY EXTENSIONS AT HINDUPUR S |
TATA PROJECTS LIMITED |
31-03-2016 |
|
7,71,39,765.79 |
0.00 |
40.24 |
| PE-12-03-06 |
400KV QMDC HINDUPUR -URAVAKONDA LI |
TATA PROJECTS LIMITED |
31-03-2016 |
|
16,85,97,862.10 |
0.00 |
200.47 |
| PE-12-03-07 |
400/220 KV HINDUPUR SS |
TATA PROJECTS LIMITED |
31-03-2016 |
31-01-2018 |
67,17,90,391.32 |
58,01,327.00 |
62.43 |
| PE-12-03-08 |
ESIA&ESMP-ELECTRICAL PROJECTS-KDP 400KV |
CHOLAMANDALAM MS RISK SERVICES LTD |
05-10-2017 |
04-12-2017 |
3,80,000.00 |
0.00 |
0 |
| PE-12-03-25 |
CONSULTANCY SERVICES-PROJECT REVIEW-KFW |
AF CONSULT SWITZERLAND LIMITED |
06-12-2018 |
|
2,80,44,517.20 |
0.00 |
0 |
| PE-12-04-01 |
400kV BE at CHITTOOR SS (TM) |
P.CHANDRA REDDY & Co. |
03-09-2014 |
|
46,30,226.98 |
0.00 |
74.35 |
| PE-12-04-02 |
400kV Twin RTPP - Peddajangampalli |
ICOMM TELE LIMITED |
29-10-2018 |
|
1,37,76,524.19 |
6,93,554.00 |
131.20 |
| PE-12-04-03 |
400kV Peddajangampalli -Chittoor DC |
ICOMM TELE LIMITED |
09-07-2019 |
|
4,24,95,010.76 |
0.00 |
27.98 |
| PE-12-04-03 |
400kV Peddajangampalli -Chittoor DC |
BUREAU VERITAS INDIA PRIVATE LIMITE |
31-01-2018 |
04-05-2018 |
13,71,750.00 |
0.00 |
0 |
| PE-15-01-03 |
400kV BE AT NARNOOR 400KV SS (QUAD) |
MEGHA ENGINEERING & INFRASTRUCTURES |
03-08-2015 |
02-11-2016 |
16,30,356.09 |
0.00 |
0 |
| PE-15-01-04 |
400KV QMDC NARNOOR-GANI LINE |
MEGHA ENGINEERING & INFRASTRUCTURES |
23-09-2015 |
25-09-2016 |
23,29,297.00 |
0.00 |
340.93 |
| PE-15-01-05 |
400/220 KV GANI SS |
MEGHA ENGINEERING & INFRASTRUCTURES |
03-08-2015 |
02-11-2017 |
5,38,06,041.48 |
0.00 |
108.78 |
| PE-16-02-01 |
400/220 KV TALARICHERUVU SS |
TATA PROJECTS LIMITED |
24-06-2017 |
23-09-2018 |
82,37,68,397.98 |
2,02,28,380.00 |
78.41 |
| PE-16-02-02 |
TALARICHERUVU LINE |
ICOMM TELE LIMITED |
16-09-2015 |
15-12-2016 |
78,76,711.08 |
0.00 |
0 |
| PE-16-02-02 |
TALARICHERUVU LINE |
TATA PROJECTS LIMITED |
08-06-2017 |
23-08-2018 |
6,69,63,589.29 |
0.00 |
125.13 |
| SI-14-09-03 |
125 MVAR BUS RECTOR AT NARNOOR |
GE T&D INDIA LIMITED |
18-07-2016 |
17-07-2017 |
1,83,89,866.16 |
0.00 |
51.62 |
| SI-15-25-05 |
LILO OF KPTM-CHITTOR 400kv QMDC LINE |
KALPATARU POWER TRANSMISSION LIMITE |
31-01-2018 |
29-04-2019 |
1,59,09,04,545.56 |
0.00 |
3.30 |
| SI-15-25-06 |
400/220/132kV RACHGUNEERIi SS |
KALPATARU POWER TRANSMISSION LIMITE |
31-01-2018 |
13-05-2019 |
1,02,90,51,378.15 |
16,77,53,164.00 |
138.87 |
| SI-15-26-02 |
LILO OF RTPP(IV)-CTR TO KALIKIRI SS |
MEIL-EMC LIMITED (JV) |
16-09-2015 |
|
6,40,13,589.15 |
0.00 |
35.30 |
| SI-15-26-03 |
400/220 KV KALIKIRI SS |
MEIL-EMC LIMITED (JV) |
16-09-2015 |
22-06-2017 |
25,92,33,714.18 |
2,91,198.00 |
125.69 |
| SI-15-26-03 |
400/220 KV KALIKIRI SS |
CG POWER AND INDUSTRIAL SOLUTIONS L |
21-12-2017 |
27-04-2018 |
12,39,000.05 |
0.00 |
6502.80 |
| SI-17-07-01 |
125 MVAR BUS RECTOR AT CHITTOR |
STERLING AND WILSON PRIVATE LIMITED |
18-03-2019 |
17-03-2020 |
3,81,48,440.02 |
30,60,984.00 |
18.41 |
| SI-19-10-01 |
EREC. OF 125MVAR BUS REACTOR-RACHAGUNNER |
KALPATARU POWER TRANSMISSION LIMITE |
05-10-2018 |
04-10-2019 |
2,88,54,479.39 |
0.00 |
0 |
| PE-12-02-05 |
220KV DC LN MYDKUR-PORUMAMILLA R-II |
P.CHANDRA REDDY & Co. |
19-12-2013 |
|
4,14,27,619.16 |
1,73,801.00 |
32.88 |
| PE-12-02-28 |
132KV LILO SZLON-JMADGU TO 400 KV SS JMD |
MEGHA ENGINEERING & INFRASTRUCTURES |
05-01-2018 |
11-07-2019 |
8,73,62,682.50 |
1,40,41,794.00 |
62.24 |
| PE-12-03-10 |
ESIA & ESMP OF ELECTRICAL PROJECTS-KDP |
CHOLAMANDALAM MS RISK SERVICES LTD |
05-10-2017 |
04-12-2017 |
6,31,000.01 |
2,72,958.00 |
77.75 |
| SI-13-07-01 |
132KV DC/SC LN RAJAMPET- C.ORAMPAD |
SHILPA ELECTRICAL INFRA TECH (INDIA |
26-04-2018 |
|
9,95,95,276.44 |
2,08,66,325.00 |
51.55 |
| SI-13-07-02 |
132/33KV SUB-STATION AT CHINNAVORAMPADU |
SHILPA ELECTRICAL INFRA TECH (INDIA |
26-04-2018 |
|
5,75,90,565.98 |
57,05,792.00 |
68.42 |
| SI-13-07-03 |
132KV BAY EXTN. AT RAJAMPETA |
SHILPA ELECTRICAL INFRA TECH (INDIA |
26-04-2018 |
|
85,10,260.79 |
3,04,655.00 |
102.33 |
| SI-16-01-01 |
220KV BAY AT 220KV CKPALLY SS |
RR DURAFABS PRIVATE LIMITED |
01-12-2017 |
30-11-2018 |
3,90,523.26 |
0.00 |
0 |
| SI-16-11-01 |
2NOS 132 KV BAYS AT RCTY FR T.SUNDUPALLI |
P.CHANDRA REDDY & Co. |
03-12-2018 |
|
1,20,57,632.07 |
71,763.00 |
0.59 |
| SI-16-11-02 |
132KV DC LINE RCTY-T.SUNDUPALLI |
P.CHANDRA REDDY & Co. |
03-12-2018 |
|
12,86,17,022.95 |
2,86,75,873.00 |
22.29 |
| SI-16-11-03 |
132/33 KV SS T.SUNDUPALLI |
P.CHANDRA REDDY & Co. |
03-12-2018 |
|
7,81,51,500.72 |
4,79,190.00 |
0.61 |
| SI-16-18-01 |
132/33KV SS AT SATELLITE CITY KADAPA |
P.CHANDRA REDDY & Co. |
03-12-2018 |
02-07-2021 |
7,86,21,696.91 |
1,38,61,337.00 |
17.63 |
| SI-16-18-02 |
132KV DC/SC C.K.PALLI-SATELLITECITY |
P.CHANDRA REDDY & Co. |
03-12-2018 |
22-08-2021 |
14,27,56,800.01 |
5,14,26,896.00 |
36.02 |
| SI-16-18-03 |
132KV BAY AT 220KV C.K.PALLI SS |
P.CHANDRA REDDY & Co. |
03-12-2018 |
02-07-2021 |
1,39,70,204.99 |
13,53,300.00 |
9.68 |
| SI-19-07-01 |
132/33KV SS AT NALLACHERUVUPALLI |
DEEPAK GALVANISING & ENGINEERING |
25-06-2020 |
|
7,21,81,818.33 |
1,78,27,028.00 |
24.69 |
| SI-19-07-02 |
132KV DC LN FR 220KV PULIVENDULA-N.PALLI |
DEEPAK GALVANISING & ENGINEERING |
25-06-2020 |
|
9,67,78,075.30 |
2,62,08,222.00 |
27.08 |
| SI-19-07-03 |
132KV BAYS AT 220KV PULIVENDULA SS |
DEEPAK GALVANISING & ENGINEERING |
25-06-2020 |
|
1,21,36,337.31 |
21,98,452.00 |
18.11 |
| Kurnool |
ECV 76,45,09,131 Crs Budget Estimates FY-22 49,35,03,248 Crs Financial Progress(%) 64.5%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| BL-19-05-01 |
220KV DC/SCLN-SETTIPALLI--RTSS VELDURTHY |
MAHENDRA CONSTRUCTIIONS |
10-06-2020 |
|
3,17,55,716.59 |
0.00 |
0 |
| PE-12-02-10 |
220KV DC LN 400KV JMADUGU-BETAMCHER |
IVRCL LIMITED |
18-11-2013 |
|
2,18,88,369.28 |
0.00 |
0 |
| PE-12-02-10 |
220KV DC LN 400KV JMADUGU-BETAMCHER |
MEGHA ENGINEERING & INFRASTRUCTURES |
05-02-2018 |
04-05-2019 |
47,65,33,654.16 |
15,38,35,006.00 |
64.90 |
| PE-12-02-10 |
220KV DC LN 400KV JMADUGU-BETAMCHER |
Sr.DIVISIONAL FINANCE MANAGER - GUN |
19-08-2020 |
|
16,96,942.24 |
0.00 |
0 |
| PE-12-02-26 |
220/132KV SS AT BETAMCHERLA |
MEGHA ENGINEERING & INFRASTRUCTURES |
10-02-2018 |
04-05-2019 |
16,06,86,222.46 |
1,20,42,559.00 |
84.14 |
| PE-12-03-11 |
ESIA & ESMP OF ELECTRICAL PROJECTS-KNL |
CHOLAMANDALAM MS RISK SERVICES LTD |
05-10-2017 |
|
7,71,000.00 |
1,38,468.00 |
89.96 |
| SI-17-22-01 |
33KV FEATURES AT 220/11KV KRISHNAGIRI SS |
ABHI TRANSMISSIONS PRIVATE LIMITED |
18-01-2019 |
|
3,52,32,115.18 |
64,42,323.00 |
69.16 |
| SI-17-23-01 |
33KV FEATURES AT 220/11KV NANSURALLA SS |
ABHI TRANSMISSIONS PRIVATE LIMITED |
18-01-2019 |
|
3,59,45,111.94 |
57,45,419.00 |
66.62 |
| Krishna |
ECV 6,88,78,72,620 Crs Budget Estimates FY-22 2,25,72,98,548 Crs Financial Progress(%) 32.7%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| PE-07-01-02 |
400KV TMDC LINE JUJJUR TO SATTENAPALLI |
GE T&D INDIA LIMITED |
13-03-2014 |
17-03-2016 |
1,01,36,283.34 |
0.00 |
0 |
| PE-09-01-01 |
400kV QMDC Krishnapatnam-Bonapply Line |
ELECTRICAL MANUFACTURING COMPANY |
28-07-2011 |
27-03-2013 |
1,25,49,426.37 |
0.00 |
393.71 |
| PE-12-01-03 |
KKOTA -VEMAGIRI TMDC (sch-A, SchB-1) |
EMC LTD - MEIL (JV) |
25-11-2015 |
24-05-2017 |
47,11,50,443.98 |
0.00 |
16.49 |
| PE-12-01-07 |
400/220 KV KAMAVARAPUKOTA SS |
GE T&D INDIA LIMITED |
13-03-2014 |
17-03-2016 |
7,82,88,716.45 |
0.00 |
134.52 |
| PE-12-01-07 |
400/220 KV KAMAVARAPUKOTA SS |
ICOMM TELE LIMITED |
01-04-2015 |
|
1,43,98,909.62 |
0.00 |
0 |
| SI-14-07-05 |
400KV BAY EXTNS AT SATTENAPALLI SS |
EMC LTD - MEIL (JV) |
30-11-2015 |
27-06-2017 |
14,83,03,002.42 |
0.00 |
16.05 |
| SI-14-07-06 |
400/220 KV PODILI SUBSTATION |
EMC LTD - MEIL (JV) |
30-11-2015 |
25-08-2017 |
82,40,85,814.37 |
0.00 |
27.06 |
| SI-14-07-07 |
400KV TMDC PODILI-SATTENAPALLY LINE |
ICOMM TELE LIMITED |
16-09-2015 |
15-12-2016 |
25,80,29,208.97 |
0.00 |
57.00 |
| SI-14-07-08 |
3RD 315 MVA ICT AT 400KV VEMAGIRI SS |
EMC LTD - MEIL (JV) |
30-11-2015 |
01-04-2017 |
1,01,07,088.86 |
0.00 |
29.65 |
| SI-14-07-09 |
220kV DCLILO(4.5km)-4KPODILI-(PODILI-NLR |
EMC LTD - MEIL (JV) |
03-04-2019 |
25-12-2019 |
7,86,22,686.47 |
0.00 |
0 |
| SI-14-11-01 |
400KV QMDC LINE KKOTA-CHINNAKORUKONDI |
KEC INTERNATIONAL LIMITED |
21-03-2014 |
|
1,68,90,291.73 |
0.00 |
74.63 |
| SI-17-07-02 |
125 MVAR BUS RECTOR AT SATTENAPALLY |
STERLING AND WILSON PRIVATE LIMITED |
06-02-2019 |
05-02-2020 |
3,52,15,679.97 |
0.00 |
11.55 |
| SI-18-01-01 |
400/220 KV THALLAYAPALEM GIS |
LARSEN & TOUBRO LIMITED |
01-10-2018 |
20-03-2020 |
1,90,63,75,442.27 |
68,23,42,410.00 |
41.36 |
| SI-10-01-02 |
132 KV DC LINE NUZVID TO NARSAPURAM |
P.CHANDRA REDDY & Co. |
25-02-2017 |
05-06-2018 |
6,84,52,991.07 |
13,62,808.00 |
28.02 |
| SI-12-03-02 |
220KV DC LINE GUNADALA- NUNNA |
CONTINENTAL TRANS TECH PRIVATE LIMI |
20-08-2018 |
|
55,07,82,059.38 |
2,50,81,873.00 |
60.09 |
| SI-12-04-01 |
132KV BAY AT NUNNA 220KV SS FOR |
YANTRA EPCOM SOLUTIONS PVT.LTD. |
17-04-2018 |
16-10-2018 |
58,05,393.65 |
0.00 |
77.89 |
| SI-12-04-03 |
132/33 KV SS GANNAVARAM |
YANTRA EPCOM SOLUTIONS PVT.LTD. |
17-04-2018 |
16-10-2018 |
2,95,77,187.93 |
0.00 |
45.32 |
| SI-16-03-01 |
132KV BAY EXTNS AT 220KV KONDAPALLI |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
02-03-2020 |
11,786.11 |
0.00 |
0 |
| SI-16-03-02 |
132 KV KONDAPALLI TO MYLAVARAM LINE |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
02-03-2020 |
1,80,46,718.87 |
0.00 |
0 |
| SI-16-03-03 |
132/33 KV SS AT MYALAVARAM |
STERLING AND WILSON PRIVATE LIMITED |
03-12-2018 |
02-03-2020 |
5,38,44,896.23 |
1,02,96,038.00 |
19.12 |
| SI-16-03-03 |
132/33 KV SS AT MYALAVARAM |
STERLING AND WILSON PRIVATE LTD |
03-12-2018 |
02-03-2020 |
12,44,82,949.17 |
19,03,077.00 |
11.77 |
| SI-16-03-04 |
132KV LILO OF KONDAPALLI-KHAMBHAMPADU |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
02-03-2020 |
11,786.11 |
0.00 |
0 |
| SI-16-03-05 |
132KV LILO OF NUZVID-KHAMBHAMPADU |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
02-03-2020 |
23,586.11 |
0.00 |
0 |
| SI-16-04-01 |
132KV BAY AT GUDIVADA FOR 2ND CKT |
LAKSHMI TRANSCON PVT.LTD. |
13-12-2018 |
|
62,94,625.35 |
0.00 |
0 |
| SI-16-04-02 |
132 KV CH.KOTA TO B.MILLI DC LINE |
STERLING AND WILSON PRIVATE LTD - ( |
17-12-2018 |
|
12,94,98,403.18 |
47,02,973.00 |
3.63 |
| SI-16-04-03 |
132/33 KV SS AT BANTUMILLI |
STERLING AND WILSON PRIVATE LTD - ( |
17-12-2018 |
|
7,54,24,056.33 |
56,06,545.00 |
7.43 |
| SI-16-04-04 |
132KV BAYS AT CH.KOTA(3NOS.) |
LAKSHMI TRANSCON PVT.LTD. |
13-12-2018 |
|
1,35,54,531.22 |
0.00 |
0 |
| SI-16-04-05 |
2ND CKT ON 132kVDC/SC GUDIVADA-Ch.KOTA |
LAKSHMI TRANSCON PVT.LTD. |
13-12-2018 |
|
1,82,89,455.93 |
0.00 |
0 |
| SI-16-05-01 |
132KV BAY EXTN AT 220KV GUNADALA SS |
RAHUL CABLES PVT.LTD. (JV with) |
09-02-2018 |
|
1,03,74,668.54 |
0.00 |
32.27 |
| SI-16-05-02 |
132KV BAY EXTN AT 220KV GUNADALA SS |
RAHUL CABLES PVT.LTD. |
09-02-2018 |
|
37,87,03,676.25 |
0.00 |
0 |
| SI-16-05-02 |
132 KV XLPE CABLE GUNADALA- M.PURAM |
RAHUL CABLES PVT.LTD. (JV with) |
09-02-2018 |
08-05-2019 |
60,66,47,162.29 |
33,29,318.00 |
57.65 |
| SI-16-05-03 |
132/33KV GIS AT MOGHALRAJPURAM |
RAHUL CABLES PVT.LTD. (JV with) |
09-02-2018 |
30-06-2021 |
11,59,45,971.33 |
5,25,37,486.00 |
48.72 |
| SI-18-15-01 |
2ND CKT STRNG FROM CHILAKALLU-NANDIGAMA |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
2,19,59,924.26 |
0.00 |
0 |
| SI-18-15-02 |
132KV BAY EXTEN. AT 132KV CHILAKALLU SS |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
55,91,532.66 |
0.00 |
0 |
| SI-18-15-03 |
132KV BAY EXTEN. AT 132KV NANDIGAMA SS |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
43,39,328.80 |
0.00 |
0 |
| SI-18-22-01 |
R/O LYNX COND WITH HTLS-GDL-AUTONAGAR |
J.S.K.INDUSTRIES PRIVATE LIMITED |
29-11-2019 |
|
1,23,98,427.67 |
82,06,881.00 |
66.19 |
| SI-18-22-02 |
132KV BAY EXTENSION AT 132KV AUTONAGAR |
J.S.K.INDUSTRIES PRIVATE LIMITED |
29-11-2019 |
|
16,46,137.70 |
6,05,211.00 |
36.76 |
| SI-18-22-03 |
132KV BAY EXTENSION AT 220KV GUNADALA |
J.S.K.INDUSTRIES PRIVATE LIMITED |
29-11-2019 |
|
16,46,137.70 |
7,75,124.00 |
47.08 |
| SI-18-42-01 |
2ND CKT STRNG-132KV NUZVID-KHAMBAMPADU |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
4,86,48,869.94 |
0.00 |
0 |
| SI-18-42-02 |
132KV BAY EXTENSION AT 132KV NUZVID SS |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
35,76,966.81 |
0.00 |
0 |
| SI-18-42-03 |
132KV BAY EXTEN AT 132KV KHAMBAMPADU SS |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
42,88,104.46 |
0.00 |
0 |
| SI-18-43-01 |
2ND CKT STRNG-132KV PAMARRU-AVANIGADDA |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
2,52,69,045.14 |
0.00 |
0 |
| SI-18-43-02 |
132KV BAY EXTENSION AT 132KV PAMARRU SS |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
45,18,882.97 |
0.00 |
0 |
| SI-18-43-03 |
132KV BAY EXTN. AT 132KV AVANIGADDA SS |
A.R. CONSTRUCTIONS PVT LTD |
18-08-2020 |
|
52,66,132.70 |
0.00 |
0 |
| SI-19-03-01 |
132/33KV SUB-STATION AT VUYYURU |
KISHORE INFRASTRUCTURES PVT.LTD |
12-03-2020 |
|
5,96,29,566.07 |
0.00 |
0 |
| SI-19-03-02 |
LILO -KANUMOLU-PAMMARRU LN TO VUYYURU SS |
KISHORE INFRASTRUCTURES PVT.LTD |
12-03-2020 |
|
15,95,25,177.82 |
0.00 |
0 |
| SI-19-11-01 |
220/132/33KV TIRUVURU SS,KRISHNA DIST. |
KMV PROJECTS LIMITED |
16-10-2020 |
03-09-2021 |
14,28,91,614.45 |
0.00 |
0 |
| SI-19-11-02 |
220KV LILO OF KTPS-NUNNA LN TO TIRUVURU |
KMV PROJECTS LIMITED |
16-10-2020 |
03-09-2021 |
7,41,07,779.34 |
0.00 |
0 |
| SI-19-11-03 |
132KV DC LN FROM NARSAPURAM TO TIRUVURU |
KMV PROJECTS LIMITED |
16-10-2020 |
03-09-2021 |
9,69,05,394.03 |
0.00 |
0 |
| SI-19-11-04 |
132KVLILO-KAMBHAMPADU-NUZVIDU TO TIRUVUR |
KMV PROJECTS LIMITED |
16-10-2020 |
03-09-2021 |
7,95,96,293.26 |
0.00 |
0 |
| SI-19-11-05 |
132KV BAY AT NARSAPURAM FOR TIRUVURU |
KMV PROJECTS LIMITED |
16-10-2020 |
03-09-2021 |
69,02,856.22 |
0.00 |
0 |
| SI-19-12-01 |
132/33KV SS AT RAMANAKKAPETA |
G.V.PRATAP REDDY |
27-08-2020 |
|
5,92,39,548.58 |
0.00 |
0 |
| Nellore |
ECV 3,08,48,46,621 Crs Budget Estimates FY-22 1,64,76,56,811 Crs Financial Progress(%) 53.4%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| SI-11-04-01 |
220KV BAYS AT MANUBOLU SS |
SRI MAHEEJA CONSTRUCTIONS |
02-08-2018 |
|
8,33,876.54 |
13,13,637.00 |
157.53 |
| SI-11-04-02 |
220KV BAYS AT SULLURPET SS |
SRI MAHEEJA CONSTRUCTIONS |
02-08-2018 |
|
83,746.64 |
0.00 |
0 |
| SI-14-01-01 |
132KV BAY AT ATMAKUR 220KV SS |
STERLING AND WILSON PRIVATE LIMITED |
08-03-2017 |
15-12-2018 |
40,08,822.91 |
0.00 |
133.81 |
| SI-14-01-02 |
132 KV DC/SC LN ATMAKUR-VINJAMUR |
STERLING AND WILSON PRIVATE LIMITED |
08-03-2017 |
15-12-2018 |
8,61,35,725.32 |
0.00 |
38.59 |
| SI-14-01-02 |
132 KV DC/SC LN ATMAKUR-VINJAMUR |
GODREJ & BOYCE MFG. CO. LTD. |
09-03-2016 |
07-09-2017 |
6,34,352.90 |
0.00 |
0 |
| SI-14-01-03 |
132/33KV SS AT VINJAMUR |
STERLING AND WILSON PRIVATE LIMITED |
08-03-2017 |
15-12-2018 |
6,02,34,881.67 |
0.00 |
111.09 |
| SI-15-02-01 |
132KV BAY AT KALLURIPALI FOR KORTURU |
ASTER PRIVATE LIMITED |
07-06-2017 |
22-04-2019 |
1,18,68,162.45 |
5,66,658.00 |
49.61 |
| SI-15-02-02 |
132KV DC KALLURIPALLI - KORUTURU |
ASTER PRIVATE LIMITED |
07-06-2017 |
30-09-2019 |
13,72,79,753.32 |
25,50,555.00 |
21.73 |
| SI-15-02-03 |
132/33KV SS KORUTURU |
ASTER PRIVATE LIMITED |
07-06-2017 |
30-08-2019 |
6,16,65,383.61 |
89,09,088.00 |
167.19 |
| SI-15-04-01 |
132KV MANUBOLU TO KADIVEDU LINE |
STERLING AND WILSON PRIVATE LTD - ( |
17-12-2018 |
|
10,69,70,977.06 |
1,47,03,187.00 |
20.52 |
| SI-15-04-02 |
132KV BAY EXTENSION AT MANUBOLU |
STERLING AND WILSON PRIVATE LTD - ( |
17-12-2018 |
|
2,23,05,012.46 |
53,009.00 |
4.67 |
| SI-15-04-03 |
132KV AT KADIVEDU |
STERLING AND WILSON PRIVATE LTD - ( |
17-12-2018 |
|
8,02,05,740.07 |
4,04,456.00 |
5.55 |
| SI-15-05-01 |
132KV LILO TO ATMAKR FROM NELLORE-ATMAK |
STERLING AND WILSON PRIVATE LIMITED |
08-03-2017 |
15-12-2018 |
3,74,38,143.82 |
0.00 |
48.85 |
| SI-15-05-02 |
132KV LILO TO ATMAKR FROM UDYGIR-ATMAKUR |
STERLING AND WILSON PRIVATE LIMITED |
08-03-2017 |
15-12-2018 |
4,40,15,059.09 |
0.00 |
91.72 |
| SI-15-05-03 |
220KV LILO OF PODILI-NELLORE I&II |
STERLING AND WILSON PRIVATE LIMITED |
08-03-2017 |
15-12-2018 |
8,36,36,989.49 |
0.00 |
60.61 |
| SI-15-05-04 |
220/132KV SS ATMAKUR |
STERLING AND WILSON PRIVATE LIMITED |
08-03-2017 |
15-12-2018 |
16,45,68,735.06 |
0.00 |
83.69 |
| SI-15-06-01 |
132KV BAY AT MANBOLU FOR KALLURPALI |
ASTER PRIVATE LIMITED |
07-06-2017 |
06-06-2018 |
76,74,112.67 |
0.00 |
186.74 |
| SI-15-06-02 |
132KV MANUBOLU TO KALLURUPALLI LINE |
ASTER PRIVATE LIMITED |
07-06-2017 |
30-09-2019 |
11,83,94,222.09 |
1,24,62,052.00 |
41.31 |
| SI-15-06-03 |
132/33KV SS KALLURIPALLI |
ASTER PRIVATE LIMITED |
07-06-2017 |
30-08-2019 |
6,19,31,498.73 |
1,00,65,566.00 |
101.67 |
| SI-15-07-01 |
132/33KV SS DAGADARTHI (KATRAYAPADU |
AMARA RAJA POWER SYSTEMS LIMITED |
17-02-2017 |
19-08-2019 |
7,26,62,097.81 |
0.00 |
49.09 |
| SI-15-08-01 |
132 BAYS AT MANUBOLU FOR RAPUR |
PMR CONSTRUCTIONS INDIA PVT.LTD. |
01-06-2016 |
19-07-2017 |
31,05,256.52 |
0.00 |
42.09 |
| SI-15-08-02 |
132KV DC LINE MANUBOLU TO RAPUR |
PMR CONSTRUCTIONS INDIA PVT.LTD. |
01-06-2016 |
19-07-2017 |
1,82,02,083.30 |
0.00 |
11.39 |
| SI-15-08-03 |
132KV SS AT RAPUR IN NELLORE DT. |
PMR CONSTRUCTIONS INDIA PVT.LTD. |
01-06-2016 |
19-07-2017 |
2,39,94,749.08 |
74,146.00 |
64.74 |
| SI-16-06-01 |
132KV LILO TO RACHARLAPADU FROM NTS-ALLU |
AMARA RAJA POWER SYSTEMS LIMITED |
17-02-2017 |
09-11-2018 |
3,75,73,781.23 |
0.00 |
58.07 |
| SI-16-06-02 |
132KV LILO TO RACHRLPDU FROM KAVALI-ALLU |
AMARA RAJA POWER SYSTEMS LIMITED |
17-02-2017 |
17-08-2018 |
7,21,43,952.55 |
0.00 |
43.81 |
| SI-16-06-03 |
132KV DC LINE FROM RACHRLPADU TO DAGADAR |
AMARA RAJA POWER SYSTEMS LIMITED |
17-02-2017 |
17-08-2018 |
13,77,49,301.55 |
0.00 |
15.53 |
| SI-16-06-04 |
220KV LILO LINE TO RACHARLAPADU SS IFF |
AMARA RAJA POWER SYSTEMS LIMITED |
17-02-2017 |
29-03-2018 |
4,46,47,409.87 |
0.00 |
45.31 |
| SI-16-06-05 |
220/132/33KV SS RACHARLAPADU IFFCO |
AMARA RAJA POWER SYSTEMS LIMITED |
17-02-2017 |
17-08-2018 |
13,92,22,672.53 |
0.00 |
43.47 |
| SI-16-25-01 |
132KV DC LINE NAIDUPEAT TO GOTTIPROLU |
P.CHANDRA REDDY & Co. |
05-07-2018 |
|
18,90,72,926.35 |
1,01,59,003.00 |
66.28 |
| SI-16-25-02 |
132KV BAY EXTENSION AT NAIDUPETA |
P.CHANDRA REDDY & Co. |
05-07-2018 |
|
1,37,03,184.04 |
6,61,656.00 |
40.02 |
| SI-16-25-03 |
EREC OF 132/33 KV SS GOTTIPROLU IN NLR |
P.CHANDRA REDDY & Co. |
05-07-2018 |
|
7,72,48,027.26 |
1,13,72,698.00 |
77.71 |
| SI-17-17-01 |
220/132/33kV SS at Menakuru / Naidupeta |
KALPATARU POWER TRANSMISSION LIMITE |
03-04-2018 |
06-06-2019 |
47,58,13,744.23 |
1,97,75,402.00 |
59.37 |
| SI-17-17-02 |
220KV DCLINE FROM RACHAGANNERU-NAIDUPETA |
KALPATARU POWER TRANSMISSION LIMITE |
03-04-2018 |
06-06-2019 |
19,15,57,115.71 |
4,24,71,037.00 |
52.70 |
| SI-17-17-03 |
132KV DC LN- 220KVNAIDUPETA-132KVMENAKUR |
KALPATARU POWER TRANSMISSION LIMITE |
03-04-2018 |
06-06-2019 |
4,25,21,240.38 |
63,26,021.00 |
14.88 |
| SI-17-17-04 |
132KV LILO OF132KVGUDURU-NAIDUPETA SC LN |
KALPATARU POWER TRANSMISSION LIMITE |
03-04-2018 |
06-06-2019 |
7,12,26,817.78 |
92,51,669.00 |
13.61 |
| SI-17-17-05 |
132KV BAY AT 132KV MENAKURU SS |
KALPATARU POWER TRANSMISSION LIMITE |
03-04-2018 |
06-06-2019 |
1,45,30,497.96 |
0.00 |
21.69 |
| SI-18-30-01 |
2NDCKT STRINGING ON 132KV GUDUR-CHENDODU |
JKV INFRACON (I) PVT LIMITED [JV] |
30-04-2020 |
29-04-2021 |
2,53,73,481.24 |
1,26,57,876.00 |
49.88 |
| SI-18-30-02 |
LILO-2ND CKT-GUDUR-CHENDODU TO MANUBOLU |
JKV INFRACON (I) PVT LIMITED [JV] |
30-04-2020 |
29-04-2021 |
1,57,88,909.07 |
59,96,752.00 |
37.98 |
| SI-18-30-03 |
132KV BAY EXTNS AT 132KV GUDUR SS |
JKV INFRACON (I) PVT LIMITED [JV] |
30-04-2020 |
29-04-2021 |
65,66,457.12 |
19,97,530.00 |
30.42 |
| SI-18-30-04 |
132KV BAY EXTNS AT 132KV CHENDODU SS |
JKV INFRACON (I) PVT LIMITED [JV] |
30-04-2020 |
29-04-2021 |
65,52,404.49 |
18,06,214.00 |
27.56 |
| SI-18-30-05 |
2 NOS 220KV BAY AT 400KV MANUBOLU SS |
JKV INFRACON (I) PVT LIMITED [JV] |
30-04-2020 |
29-04-2021 |
1,20,41,865.12 |
53,19,013.00 |
44.17 |
| SI-19-06-01 |
EREC OF 132/33KV SS Ananthasgram-2x 31.5 |
JKV INFRACON (I) PVT LIMITED [JV] |
30-04-2020 |
29-04-2021 |
6,76,57,980.40 |
3,76,27,727.00 |
55.61 |
| SI-19-06-02 |
132KV DC LINE ATMKR TO ANANTSGRM |
JKV INFRACON (I) PVT LIMITED [JV] |
30-04-2020 |
29-04-2021 |
22,46,68,926.02 |
12,74,61,678.00 |
56.73 |
| SI-19-06-03 |
132KV BAY EXTENSION AT 220KV ATMAKUR SS |
JKV INFRACON (I) PVT LIMITED [JV] |
30-04-2020 |
29-04-2021 |
1,13,36,543.96 |
46,78,505.00 |
41.26 |
| Prakasam |
ECV 82,16,11,276 Crs Budget Estimates FY-22 15,08,28,519 Crs Financial Progress(%) 18.3%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| SI-16-07-01 |
132KV DC PODILI - CHINNARIKATLA |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
|
15,61,69,883.57 |
2,07,89,725.00 |
24.12 |
| SI-16-07-02 |
132KV BAY AT PODILI SS |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
|
1,59,41,808.06 |
0.00 |
12.22 |
| SI-16-07-03 |
132KV SS AT CHINNARIKATLA |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
|
7,11,65,976.89 |
50,87,917.00 |
42.60 |
| SI-16-08-01 |
132KV DC PODILI - EAST GANGAVARAM |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
|
12,28,08,669.20 |
1,55,13,685.00 |
12.63 |
| SI-16-08-02 |
132KV BAY AT PODILI SS |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
|
1,74,81,874.48 |
33,86,269.00 |
82.93 |
| SI-16-08-03 |
132KV SS AT EAST GANGAVARAM |
STERLING AND WILSON PRIVATE LTD - ( |
03-12-2018 |
19-07-2021 |
8,51,36,864.23 |
0.00 |
8.09 |
| SI-17-20-01 |
132/33KV SUB-STATION AT ULAVAPADU |
SRI BALAJI INFRA PROJECTS |
20-03-2019 |
14-02-2020 |
5,56,51,485.93 |
0.00 |
0 |
| SI-17-20-02 |
132KV DC/SC LINE FROM KANDUKUR-ULAVAPADU |
SRI BALAJI INFRA PROJECTS |
12-12-2018 |
14-02-2020 |
4,33,02,714.36 |
0.00 |
0 |
| SI-17-20-03 |
132KV BAY EXTENSION AT 220KV KANDUKUR SS |
SRI BALAJI INFRA PROJECTS |
12-12-2018 |
|
15,80,088.14 |
0.00 |
0 |
| SI-18-25-01 |
2ND CKT STRNG--132KV MEDARAMETLA-ADDANKI |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
1,73,06,033.37 |
1,04,81,991.00 |
60.56 |
| SI-18-25-02 |
132KV BAY EXTENSION AT 132KV MEDARAMETLA |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
44,09,026.07 |
11,39,398.00 |
25.84 |
| SI-18-25-03 |
132KV BAY EXTENSION AT 132KV ADDANKI SS |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
41,47,426.43 |
12,45,793.00 |
30.03 |
| SI-18-26-01 |
2NDCKT STRNG--220KV PODILI-LINGASAMUDRAM |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
3,83,58,986.58 |
1,05,46,681.00 |
27.49 |
| SI-18-26-02 |
132KV BAY EXTENSION AT 220KV PODILI SS |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
48,27,270.20 |
13,04,115.00 |
27.01 |
| SI-18-26-03 |
132KV BAY EXTN. AT 132KV LINGASAMUDRAM |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
44,67,417.54 |
12,79,478.00 |
28.64 |
| SI-18-27-01 |
2ND CKT STRINING FROM 220KV PODILI-DARSI |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
2,07,65,966.36 |
1,51,27,777.00 |
72.84 |
| SI-18-27-02 |
132KV BAY EXTENSION AT 220KV PODILI SS |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
49,65,237.22 |
14,45,988.00 |
29.12 |
| SI-18-27-03 |
132KV BAY EXTENSION AT 132KV DARSI SS |
ABHI TRANSMISSIONS PRIVATE LIMITED |
01-07-2020 |
30-06-2021 |
44,85,490.88 |
14,08,158.00 |
31.39 |
| SI-19-09-01 |
132KV XLPE UG CBL B/W 220KV&132KV ONGOLE |
PAVANI CONTROLS AND PANELS LTD |
02-09-2020 |
01-03-2021 |
12,49,07,065.98 |
0.00 |
0 |
| SI-19-09-02 |
2NOS 132KV BAY EXTN. AT 132KV ONGOLE SS |
PAVANI CONTROLS AND PANELS LTD |
02-09-2020 |
01-03-2021 |
92,31,304.69 |
0.00 |
0 |
| SI-19-09-03 |
2NOS 132KV BAY EXTN. AT 220KV ONGOLE SS |
PAVANI CONTROLS AND PANELS LTD |
02-09-2020 |
01-03-2021 |
1,45,00,686.64 |
0.00 |
0 |
| Srikakulam |
ECV 75,87,62,130 Crs Budget Estimates FY-22 51,74,66,911 Crs Financial Progress(%) 68.19%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| SI-15-31-01 |
220/132/33 KV SS PYDIBHIMAVARAM |
KMV PROJECTS LIMITED |
30-01-2018 |
20-02-2020 |
20,04,31,058.09 |
36,62,875.00 |
93.41 |
| SI-15-31-01 |
220/132/33 KV SS PYDIBHIMAVARAM |
SREE LAKSHMI ELECTRICAL SERVICES |
12-02-2020 |
03-10-2020 |
4,21,16,010.46 |
0.00 |
0 |
| SI-15-31-03 |
132 KV DCLINE PYDIBHIMAVARM-132KV SS CHI |
BHARATH ELECTRICAL WORKS |
03-12-2018 |
31-03-2020 |
11,52,34,221.47 |
93,08,378.00 |
80.16 |
| SI-15-31-04 |
132KV BAY EXTNS AT 132KV SS CHILAKAPALEM |
BHARATH ELECTRICAL WORKS |
03-12-2018 |
31-03-2020 |
1,90,80,836.48 |
0.00 |
53.73 |
| SI-15-31-05 |
220KV BAY EXTEN AT 400/220KV SS GARIVIDI |
SREE LAKSHMI ELECTRICAL SERVICES |
12-02-2020 |
03-10-2020 |
3,01,72,998.30 |
0.00 |
0 |
| SI-15-31-06 |
220KV DC LINE FROM GVD TO PYDIBHIMAVARAM |
KMV PROJECTS LIMITED |
30-01-2018 |
20-02-2020 |
35,17,27,005.79 |
1,04,71,367.00 |
64.70 |
| Visakhapatnam |
ECV 6,95,58,42,128 Crs Budget Estimates FY-22 1,81,90,14,396 Crs Financial Progress(%) 26.15%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| PE-12-01-08 |
KKOTA -VEMAGIRI TMDC (SchB-2) |
EMC LTD - MEIL (JV) |
11-03-2015 |
24-05-2017 |
39,92,65,224.91 |
37,47,896.00 |
58.42 |
| PE-18-01-02 |
400kV Polavaram HPS-Guddigudem QMDC Line |
MEGHA ENGINEERING & INFRASTRUCTURES |
07-01-2020 |
01-03-2022 |
2,46,91,41,730.48 |
93,23,774.00 |
0.37 |
| PE-18-01-03 |
2No. 400KV BAY EXTEN. AT GUDDIGUDEM SS |
MEGHA ENGINEERING & INFRASTRUCTURES |
07-01-2020 |
|
9,21,54,197.47 |
64,64,820.00 |
7.01 |
| SI-12-07-05 |
400KV QUAD KALAPAKA - GARIVIDI DC |
ELECTRICAL MANUFACTURING COMPANY |
08-09-2014 |
07-03-2016 |
32,58,17,512.53 |
3,83,07,257.00 |
117.39 |
| SI-12-07-06 |
ERECTION OF 400KV GARIVIDI SS |
ELECTRICAL MANUFACTURING COMPANY |
15-11-2014 |
29-02-2016 |
33,57,42,435.10 |
1,52,29,809.00 |
39.36 |
| SI-12-07-07 |
400KV BAY MODIFICATION AT 400KALAPAK |
ELECTRICAL MANUFACTURING COMPANY |
15-11-2014 |
|
8,21,58,403.71 |
0.00 |
0.06 |
| BL-12-02-01 |
132KV BRANDIX TO NAVALBASE POST |
SRI HARI CONSTRUCTIONS |
16-09-2016 |
15-06-2017 |
90,08,043.72 |
24,27,494.00 |
26.94 |
| BL-12-02-02 |
BAYS AT BRANDIX |
SRI HARI CONSTRUCTIONS |
16-09-2016 |
15-06-2017 |
10,80,176.94 |
0.00 |
0 |
| BL-12-02-03 |
BAYS AT NAVALBASE POST |
SRI HARI CONSTRUCTIONS |
16-09-2016 |
15-06-2017 |
67,55,533.79 |
1,61,35,008.00 |
317.80 |
| SI-17-14-01 |
UPGRADATION OF 132KV SML SS-220KV SS |
HYDERABAD POWER INSTALLATIONS PVT L |
14-10-2019 |
13-02-2021 |
35,54,09,855.50 |
13,76,58,271.00 |
90.97 |
| SI-17-14-02 |
LILO OF 220KV KPK-DFM LINE TO 220KV SLM |
HYDERABAD POWER INSTALLATIONS PVT L |
14-10-2019 |
13-02-2021 |
12,68,88,897.90 |
0.00 |
0 |
| SI-17-17-06 |
220/132/33KV GIS SS AT ACHUTAPURAM |
SREE LAKSHMI ELECTRICAL SERVICES |
04-06-2018 |
|
5,03,487.12 |
0.00 |
0 |
| SI-17-17-06 |
220/132/33KV GIS SS AT ACHUTAPURAM |
RAHUL CABLES PVT.LTD. (JV with) |
31-08-2018 |
04-10-2020 |
60,89,43,889.62 |
12,89,84,738.00 |
21.28 |
| SI-17-17-07 |
220KV DCLINE FROM BRANDIX-ACHUTHAPURAM |
RAHUL CABLES PVT.LTD. (JV with) |
31-08-2018 |
04-10-2020 |
6,78,89,924.93 |
0.00 |
0 |
| SI-17-17-08 |
220KV BAY EXTENSION AT 220KV BRANDIX SS |
RAHUL CABLES PVT.LTD. (JV with) |
31-08-2018 |
04-10-2020 |
3,76,91,241.74 |
0.00 |
0 |
| SI-17-17-09 |
132/33KV GIS SS AT KAPULUPPADA |
RAHUL CABLES PVT.LTD. (JV with) |
31-08-2018 |
04-10-2020 |
21,81,55,752.34 |
52,07,53,436.00 |
238.70 |
| SI-17-17-10 |
132KV DC LINE(XLPE) 220KV DFMSS-GIS SS |
RAHUL CABLES PVT.LTD. (JV with) |
31-08-2018 |
04-10-2020 |
93,66,98,452.02 |
0.00 |
0 |
| SI-17-17-11 |
132KV BAY EXTENSION AT 220KV DAIRYFARM |
RAHUL CABLES PVT.LTD. (JV with) |
31-08-2018 |
04-10-2020 |
1,29,57,462.78 |
0.00 |
0 |
| SI-17-17-12 |
220/132KV CHANDNADA (KORUPROLU) SS |
RAHUL CABLES PVT.LTD. (JV with) |
08-08-2019 |
04-10-2020 |
44,68,55,759.47 |
5,82,74,567.00 |
13.04 |
| SI-17-17-13 |
LILO 220KVANRAK-SAMALKOTA & VSS-KKD LINE |
RAHUL CABLES PVT.LTD. (JV with) |
08-08-2019 |
04-10-2020 |
34,95,16,946.15 |
0.00 |
0 |
| SI-18-14-01 |
220/132KV CHANDNADA (KORUPROLU) SS |
RAHUL CABLES PVT.LTD. (JV with) |
31-08-2018 |
04-10-2020 |
7,32,07,200.00 |
0.00 |
0 |
| Vizianagaram |
ECV 41,74,23,622 Crs Budget Estimates FY-22 12,69,74,652 Crs Financial Progress(%) 30.4%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| BL-13-02-01 |
132KV BAY EXTEN AT PARVATHIPURAM |
MAHENDRA CONSTRUCTIIONS |
30-04-2019 |
|
21,666.00 |
3,47,886.00 |
1605.67 |
| BL-14-01-01 |
132KV BAY EXTENSION AT RTSS KOMATIPALLI |
VISHWANATH PROJECTS LIMITED |
07-01-2016 |
|
34,82,643.11 |
3,66,489.00 |
10.52 |
| BL-14-01-02 |
132KV LINE FROM BOBBILI TO KOMATPALLI |
VISHWANATH PROJECTS LIMITED |
07-01-2016 |
|
16,49,189.19 |
9,92,994.00 |
413.97 |
| BL-14-01-03 |
132KV BAY EXTENSION AT 220KV BOBBILI |
VISHWANATH PROJECTS LIMITED |
07-01-2016 |
|
9,91,830.51 |
78,705.00 |
7.93 |
| SI-11-01-01 |
132KV DC LN220kV Pydibimavrm-Gchodavaram |
SREE LAKSHMI ELECTRICAL SERVICES |
16-11-2018 |
27-02-2020 |
4,56,94,038.21 |
0.00 |
0 |
| SI-11-01-02 |
132/33KV SS AT G.CHODAVARAM,VZM DIST |
SREE LAKSHMI ELECTRICAL SERVICES |
16-11-2018 |
27-02-2020 |
9,23,27,696.62 |
0.00 |
0 |
| SI-11-01-03 |
132KV BAY EXTEN. AT 220KV PYDIBHIMAVARAM |
SREE LAKSHMI ELECTRICAL SERVICES |
16-11-2018 |
27-02-2020 |
1,15,53,407.90 |
0.00 |
0 |
| SI-11-05-02 |
220 KV DC LINE BOBBILI-GARVIDI |
P.CHANDRA REDDY & Co. |
04-12-2015 |
03-06-2017 |
39,57,636.90 |
0.00 |
176.89 |
| SI-11-05-03 |
1ST RECH 220KV LINE BOBBILI-ADP-1 |
HAIGREEVA INFRATECH |
28-10-2011 |
|
72,58,926.49 |
0.00 |
0 |
| SI-11-05-04 |
2ND REACH 220KV LINE BOBBILI-ADP-2 |
HAIGREEVA INFRATECH |
28-10-2011 |
|
5,09,952.20 |
0.00 |
0 |
| SI-11-05-06 |
220 KV APPAYYADORAPALEM SW S |
HAIGREEVA INFRATECH |
28-10-2011 |
|
49,16,409.62 |
0.00 |
0 |
| SI-11-05-10 |
2NOs 220KV BAYS AT 220KV GARIVIDI SS |
P.CHANDRA REDDY & Co. |
04-12-2016 |
03-06-2017 |
55,32,261.03 |
0.00 |
4.07 |
| SI-12-06-01 |
132/33KV SS AT GARBHAM |
GURPREET GALVANISING PRIVATE LIMITE |
29-08-2016 |
27-08-2017 |
3,62,22,485.28 |
0.00 |
17.47 |
| SI-12-06-02 |
132KV LINE FROM BOBBILI TO GARBHAM |
GURPREET GALVANISING PRIVATE LIMITE |
14-10-2016 |
13-10-2017 |
64,59,272.52 |
0.00 |
56.55 |
| SI-12-07-04 |
LILO OF EXIST. 220KV PDTY- GVD (PDT END) |
GURPREET GALVANISING PRIVATE LIMITE |
21-03-2016 |
20-03-2017 |
7,26,78,512.26 |
0.00 |
37.40 |
| SI-12-07-09 |
LILO OF EXIST. 220KV PDTY- GVD (GVD END) |
GURPREET GALVANISING PRIVATE LIMITE |
21-03-2016 |
20-03-2017 |
2,52,72,711.00 |
0.00 |
152.86 |
| SI-12-07-10 |
LILO OF 220KV BDPALEM-BOBIILI TO MARADAM |
GURPREET GALVANISING PRIVATE LIMITE |
21-03-2016 |
20-03-2017 |
2,25,91,177.13 |
0.00 |
24.90 |
| SI-14-03-01 |
132KV SS AT SALUR IN VZNM DISTRICT |
P.CHANDRA REDDY & Co. |
06-03-2017 |
06-09-2017 |
2,78,02,056.77 |
43,74,114.00 |
33.00 |
| SI-14-03-02 |
LINE FROM220KV BOBBILI SS TO SALUR |
P.CHANDRA REDDY & Co. |
16-06-2016 |
14-12-2017 |
92,00,750.77 |
0.00 |
94.42 |
| SI-14-03-03 |
132KV BAYS AT 220KV BOBBILI SS |
P.CHANDRA REDDY & Co. |
16-06-2016 |
03-06-2017 |
22,42,493.19 |
2,75,529.00 |
12.28 |
| SI-18-11-01 |
33KV FEATURES AT 220/132 KV BOBBILI SS |
P.CHANDRA REDDY & Co. |
06-03-2020 |
30-03-3021 |
3,70,58,506.20 |
1,25,59,159.00 |
33.89 |
| West Godavari |
ECV 2,00,33,08,942 Crs Budget Estimates FY-22 37,58,81,784 Crs Financial Progress(%) 18.7%
|
|
| Project ID |
Project Description |
Vendor Name |
Sanction Date |
Completion Date |
ECV |
Budget Estimates FY-22 |
Financial Progress (%) |
| BL-18-02-02 |
132KV METERING BAY AT 220KV DUVVA SS |
S.VIJAYA BHASKAR |
23-06-2020 |
|
1,48,60,001.65 |
0 |
0 |
| BL-18-02-03 |
132KV METERING BAY AT RTSS TANUKU |
S.VIJAYA BHASKAR |
23-06-2020 |
|
91,68,076.06 |
4,44,79,708.00 |
0 |
| BL-18-02-01 |
132KV SC LN FROM 220KV DUVVA-RTSS TANUKU |
S.VIJAYA BHASKAR |
23-06-2020 |
|
2,97,60,045.40 |
67,03,382.00 |
0 |
| PE-18-01-04 |
LILO-220KVPALLANTLA-PATTISEEMA ATGDGUDEM |
MEGHA ENGINEERING & INFRASTRUCTURES |
21-01-2020 |
|
19,01,43,597.54 |
0.00 |
23.39 |
| PE-18-01-06 |
6NO 220KV BAY EXTENSION AT 400KV GDGUDEM |
MEGHA ENGINEERING & INFRASTRUCTURES |
21-01-2020 |
|
16,75,16,585.72 |
87,28,656.00 |
4.00 |
| PE-18-01-08 |
220KV DCLN GDGUDEM-PURUSHOTHAPATNAM-5116 |
MEGHA ENGINEERING & INFRASTRUCTURES |
21-01-2020 |
20-07-2021 |
14,20,33,268.04 |
80,83,105.00 |
0 |
| SI-10-07-01 |
132/33KV NARAYANAPURAM SS |
RR DURAFABS PRIVATE LIMITED (JV) |
03-03-2020 |
05-12-2020 |
5,18,68,412.12 |
0.00 |
16.82 |
| SI-10-07-02 |
LILO NDV-BMD NARAYANAPURAM LINE |
RR DURAFABS PRIVATE LIMITED (JV) |
03-03-2020 |
05-12-2020 |
6,04,05,589.62 |
0.00 |
13.38 |
| SI-15-01-03 |
220KV LILO OF VTS-KKOTA AT 400KV KK |
BHARATH ELECTRICAL WORKS |
01-09-2018 |
31-05-2019 |
1,17,243.27 |
0.00 |
0 |
| SI-15-01-03 |
220KV LILO OF VTS-KKOTA AT 400KV KK |
P.CHANDRA REDDY & Co. |
01-03-2017 |
|
48,037.80 |
16,91,182.00 |
0 |
| SI-15-01-03 |
220KV LILO OF VTS-KKOTA AT 400KV KK |
SRI MAHEEJA CONSTRUCTIONS |
22-06-2017 |
31-12-2019 |
1,47,10,864.68 |
0.00 |
35.38 |
| SI-15-01-04 |
220KV BAY EXTENSION AT 400KV KV KOTA SS |
SRI MAHEEJA CONSTRUCTIONS |
22-06-2017 |
31-12-2019 |
7,19,38,989.72 |
32,26,709.00 |
24.15 |
| SI-15-10-04 |
132KV DUVVA-PEDATADEPALLI |
R.K.ELECTRIC AUTOMATION LIMITED |
05-01-2017 |
04-07-2018 |
10,84,59,686.71 |
33,07,800.00 |
48.97 |
| SI-17-18-01 |
220KV DCLine from 400KV K.Kota-Bhimadole |
GUPTA POWER INFRASTRUCTURE LIMITED |
10-09-2018 |
31-03-2020 |
14,44,36,865.31 |
52,52,083.00 |
55.48 |
| SI-17-18-02 |
220KV BAY EXTENSION AT220KV BHIMADOLE SS |
GUPTA POWER INFRASTRUCTURE LIMITED |
10-09-2018 |
31-03-2020 |
3,13,86,298.31 |
4,38,93,331.00 |
62.45 |
| SI-17-18-03 |
220KV BAY EXTENSION AT 400KV K.KOTA SS |
GUPTA POWER INFRASTRUCTURE LIMITED |
10-09-2018 |
31-03-2020 |
6,15,17,423.23 |
14,77,765.00 |
53.23 |
| SI-18-05-01 |
220/33KV AKIVEEDU SS IN WEST GODAVARI |
SRI RAM ENGINEERING |
22-02-2020 |
22-01-2021 |
14,32,26,422.82 |
66,67,220.00 |
30.64 |
| SI-18-05-02 |
LILO OF 220KV BHIMAVARAM-ELURU (ONE CKT) |
SRI RAM ENGINEERING |
22-02-2020 |
|
4,21,99,275.60 |
37,08,704.00 |
3.50 |
| SI-18-06-01 |
33KV FEATURES AT 220/33KV PATTISEEMA SS |
ABHI TRANSMISSIONS PRIVATE LIMITED |
20-12-2018 |
19-09-2020 |
4,98,77,643.02 |
0.00 |
31.97 |
| SI-18-16-02 |
132KV BAY EXTENSION AT 132KV PT PALLI SS |
SRI RAM ENGINEERING |
26-02-2019 |
31-05-2020 |
1,47,65,211.30 |
0.00 |
25.56 |
| SI-18-20-01 |
132/33KV SS AT DHARMAJIGUDEM |
STERLING AND WILSON PRIVATE LTD |
30-01-2020 |
27-11-2020 |
7,79,29,121.34 |
0.00 |
0 |
| SI-18-20-01 |
132/33KV SS AT DHARMAJIGUDEM |
RR DURAFABS PRIVATE LIMITED (JV) |
19-10-2020 |
|
1,49,84,458.16 |
0.00 |
0 |
| SI-18-20-02 |
132KV DC LN FR 220KV K.KOTA-DHARMAJIGUDE |
STERLING AND WILSON PRIVATE LTD - ( |
30-01-2020 |
27-11-2020 |
12,68,72,611.12 |
0.00 |
0 |
| SI-18-20-03 |
132KV BAY EXTENSION AT 220KV K.KOTA SS |
STERLING AND WILSON PRIVATE LTD - ( |
30-01-2020 |
27-11-2020 |
91,34,281.98 |
0.00 |
0 |
| SI-18-21-01 |
132/33KV SS AT DWARAKA TIRUMULA |
RR DURAFABS PRIVATE LIMITED (JV) |
19-10-2020 |
|
6,92,96,995.98 |
2,33,59,082.00 |
0 |
| SI-18-21-02 |
132KV DC LINE-LILO OF K.KOTA-BHIMADOLE |
RR DURAFABS PRIVATE LIMITED (JV) |
19-10-2020 |
|
2,96,92,978.77 |
66,73,145.00 |
0 |
| SI-19-04-01 |
LILO OF NIDADAVOLU-NALLAJERLA TO PALLANT |
SHILPA ELECTRIFICATION |
01-06-2020 |
24-02-2021 |
3,79,10,345.24 |
45,64,477.00 |
61.61 |
| SI-19-04-03 |
2 NOS 132KV BAY EXTEN. AT PALLANTLA |
SHILPA ELECTRIFICATION |
01-06-2020 |
24-02-2021 |
2,31,04,974.62 |
0.00 |
28.88 |
| SI-19-08-01 |
132/33 KV T.NARSAPURAM SS |
G.V.PRATAP REDDY [JV] K.M.V.PROJECT |
25-02-2020 |
24-02-2021 |
9,13,21,571.75 |
0.00 |
4.99 |
| SI-19-08-02 |
LILO OF 132KV LN FR 220KV K.KOTA-ASWPETA |
G.V.PRATAP REDDY [JV] K.M.V.PROJECT |
25-02-2020 |
24-02-2021 |
8,96,15,785.15 |
|
0 |
| SI-19-08-03 |
LILO OF 132KV LN FR 132KV K.KOTA-ASWPETA |
G.V.PRATAP REDDY [JV] K.M.V.PROJECT |
25-02-2020 |
24-02-2021 |
8,50,06,280.31 |
|
0 |